Production Activities

    1. Explanation of Connection Regions and Capacities
    2. Acquisition of the right to use and establishment of wind / solar measurement stations for the place where wind / solar measurement stations will be installed in the field where the project will be developed by the company established for electricity production according to the Turkish Commercial Code.
    3. Wind - solar measurement for at least 1 year at the project site or location representing the site
    4. Preparation of the Associate Application File and application
    5. Approval of the "Measurement Station Setup Report" prepared for the installed measurement stations by the General Directorate of Meteorology or Accredited institutions
    6. Submission of measurement data for at least 1 year to the General Directorate of Meteorology or Accredited institutions
    7. Approval of "Measurement Result Report" by the General Directorate of Meteorology or Accredited institutions at the end of 1 year
    8. Preparation of application information and documents announced by the Electricity Market Licensing Regulation and EMRA Board Decisions
    9. Application of associate degree on the dates announced by EMRA Board Decisions
    10. Preliminary examination of the Associate's application by EMRA
    11. Submission of the "technical evaluation result report" prepared by EIGM to EMRA for those whose preliminary examination is deemed appropriate, for those whose technical evaluation and technical evaluation of the application are deemed appropriate.
    12. Completion of the connection "competition" process by TEIAS for the applications which are evaluated in technical and in the same region.
    13. To notify the EMRA to the EMRA who is committed to paying the highest fee for the installed unit of "MW" by TEIAS.
    14. The “winner” of the company that won the competition by EMRA
    15. Obtaining all kinds of administrative permissions for the establishment of the facility by the company during the associate degree - development plan approvals - project approvals
    16. Grant of production by EMRA
    17. Completion of construction - facility acceptance
    • Approval of the projects of the facility by MENR or institutions to be authorized by MENR
    • Completing the construction and installation processes
    • Acceptance of the facility by MENR or institutions authorized by MENR
    1. Businesses

    Note: Measurements are made only for associate degree applications based on wind and solar energy.

    1. Explanation of Connection Regions and Capacities
    2. Acquisition of the right to use and establishment of wind / solar measurement stations for the place where wind / solar measurement stations will be installed in the field where the project will be developed by the company established for electricity production according to the Turkish Commercial Code.
    3. Wind - solar measurement for at least 1 year at the project site or location representing the site
    4. Preparation of the Associate Application File and application
    5. Approval of the "Measurement Station Setup Report" prepared for the installed measurement stations by the General Directorate of Meteorology or Accredited institutions
    6. Submission of measurement data for at least 1 year to the General Directorate of Meteorology or Accredited institutions
    7. Approval of "Measurement Result Report" by the General Directorate of Meteorology or Accredited institutions at the end of 1 year
    8. Preparation of application information and documents announced by the Electricity Market Licensing Regulation and EMRA Board Decisions
    9. Application of associate degree on the dates announced by EMRA Board Decisions
    10. Preliminary examination of the Associate's application by EMRA
    11. Submission of the "technical evaluation result report" prepared by EIGM to EMRA for those whose preliminary examination is deemed appropriate, for those whose technical evaluation and technical evaluation of the application are deemed appropriate.
    12. Completion of the connection "competition" process by TEIAS for the applications which are evaluated in technical and in the same region.
    13. To notify the EMRA to the EMRA who is committed to paying the highest fee for the installed unit of "MW" by TEIAS.
    14. The “winner” of the company that won the competition by EMRA
    15. Obtaining all kinds of administrative permissions for the establishment of the facility by the company during the associate degree - development plan approvals - project approvals
    16. Grant of production by EMRA
    17. Completion of construction - facility acceptance
    • Approval of the projects of the facility by MENR or institutions to be authorized by MENR
    • Completing the construction and installation processes
    • Acceptance of the facility by MENR or institutions authorized by MENR
    1. Businesses

    Note: Measurements are made only for associate degree applications based on wind and solar energy.

    Within the scope of Article 14 of the Electricity Market Law (Law) No. 6446, the Communiqué on the Implementation of the Regulation on Unlicensed Electricity Generation in the Electricity Market and the Regulation on the Unlicensed Electricity Generation in the Electricity Market was prepared and the secondary legislation in question was published in the Official Gazette dated 2/10/2013 and numbered 28783. It was published and entered into force. Purpose of Unlicensed Electricity Generation Regulation (LÜY); In the electricity market, without the obligation of obtaining a license and establishing a company in order to meet the electricity needs of the consumers from its own generation facility closest to the point of consumption, to provide small-scale generation facilities to the country's economy in ensuring supply security and to ensure the efficient use of small-scale generation resources, and to reduce the losses in the electricity network, to enable it to produce electrical energy.

    As it is known, our installed power, which was 40 MW at the end of 2014 within the scope of unlicensed electricity production, reached 6540 MW as of the end of May 2019. The public's long-awaited changes such as unlicensed Electricity Generation Regulation in the Electricity Market published in the Official Gazette dated 10/05/2019 and numbered 30770, and the Electricity Regulations Unlicensed in the Electricity Market published in the Official Gazette dated 12/05/2019 and numbered 30772, and in terms of unlicensed electricity generation. has entered a new era. Unlicensed electricity generation plants, which have been built on lands that are not suitable for agriculture so far, contributing to the increase of the share of renewable energy in our total electricity production, will be established at the same measurement point as the consumption facilities with the new period. Thus, since electricity will be consumed where it is produced, distribution and transmission investments will decrease and self-consumption will be encouraged. On the other hand, roofs covering large areas and in an idle position will provide added value.

    With the published President Decision, since the installed power upper limit of unlicensed electricity generation facilities is increased to 5 MW, since the excess investment will be taken over the energy tariff price, considering the current investment costs, the most appropriate investment for our consumers is to establish a production facility that will meet the consumption amount, not the consumption power. appears to be.

     

    Technical Assessment for unlicensed electricity generation applications in the Electricity Market under the Electricity Market, published in the Official Gazette dated 12/05/2019 and numbered 30772, is carried out by our General Directorate.

    Technical Assessment carried out by our General Directorate within the scope of LÜY.

    1. From applications based on wind or solar energy; The information included in the technical evaluation form for the applications whose connection application is approved is sent to the EIGM for technical evaluation within ten working days from the date the application is approved. Technical evaluation is concluded by EIGM within thirty days and the technical evaluation report is sent to the relevant network operator. In the event that there are errors and/or deficiencies in the information sent to the EIGM, the applicant is notified by the relevant network operators within 3 working days after the relevant determination is made to eliminate the non-compliance. In case the errors and/or deficiencies are not resolved and presented to the relevant network operator within 10 business days following the notification or if the technical evaluation report is negative as a result of the EIGM evaluation, a copy of the application documents is returned to the applicant after being transferred to the permanent data keeper.

    2. The letter of call for the connection agreement for solar energy applications, the technical evaluation report of which is positive, is notified to the relevant person by the relevant network operator upon the written application of the relevant persons within one month from the announcement of the list subject to the fifth paragraph. In this context, the positive connection opinions of the applicants who do not apply are automatically void and a copy of the application documents are returned to the applicant after they are transferred to the permanent data store.

    3. For applications based on wind energy, the technical evaluation report of the applications whose technical evaluation is deemed appropriate by the EIGM in the tenth paragraph of the Article 7 of the Regulation on Unlicensed Electricity Production in the Electricity Market is announced on the website of the EIGM until the 5th of each month. The applicant applies to TÜBİTAK Information and Information Security Advanced Technologies Research Center for technical interaction permission within thirty days from the date of the announcement. The document indicating that the said application has been made is submitted to the EIGM within thirty days from the announcement date of the EIGM. The document stating that the TÜBİTAK Information and Information Security Advanced Technologies Research Center has been applied for Technical Interaction Permit is;

    a. If it is not submitted within the deadline, the said application,

    b. In order to hold the capacity of the relevant application until the result of the technical interaction permission, if it is submitted within the deadline,

    It is reported to the related network operator by EIGM. The technical interaction permit is notified to the related network operator within ten working days by EIGM together with the technical evaluation report. If the technical evaluation report and/or the technical interaction permit is negative or if the document indicating that the application for the technical interaction permit is not submitted within the period of time, after the transfer of a copy of the application documents to the permanent data store, "applications are rejected" in the scope of item (a). provision is the supervisor and returned to the applicant.

    4. For applications based on wind energy, where the technical interaction permit and the technical evaluation report are positive, a call letter is issued to the connection agreement by the relevant network operator. The letter of call for the connection agreement is notified to the relevant person by the relevant network operator if they apply in writing within one month from the announcement of the list subject to the fifth paragraph. In this context, the positive connection opinions of the applicants who do not apply are automatically void and a copy of the application documents are returned to the applicant after they are transferred to the permanent data store.

    5. Information regarding the applications that result in positive and negative results under the provisions of the first, second, third, and fourth paragraphs are regularly announced on the website of the relevant network operator on a monthly basis, including the necessary explanations.

    6. In the call letters to the connection agreement created by the relevant network operator, it is clearly stated in which provision of this Regulation the document is issued. This document also specifies in which provision the excess energy will be evaluated. ”

    It is made within the scope of the provision.

    Click here to download the Technical Evaluation Form for Unlicensed Electricity Generation Applications Based on Solar Energy.

    Click here to download the Technical Evaluation Form for Unlicensed Electricity Generation Applications Based on Wind Energy.

    Click for Technical Interaction Analysis (TEA) Roadmap for Unlicensed Applications.

     

    It will be beneficial for applicants of wind power generation facilities to follow the website of our General Directorate in order to prevent their grievances.

    Opinions are given by managing the technical evaluation process for unlicensed production applications made to DISCOMs and evaluating the revised requests under the legislation.

    In the provinces under the responsibility of DISCOMs with the power plants planned to be established within the scope of unlicensed production applications, opinions regarding the zoning plans and the EIA reports prepared for other purposes are created.

    Applications will be considered negative in the following situations:

    • Lack of information in the technical evaluation information form,

    • The corner coordinates that make up the power plant area are not in consecutive order,

    • The unlicensed electricity facility affects the generation facility/facilities that have acquired the facilities (licensed, YEKA…) in another unlicensed and incompatible areas,

    • When the turbine coordinates specified in the application are considered to be centers, a circular area whose radius will be drawn so that the rotor blade length is overflowing beyond the land boundary specified in the application.

    As per the first and second paragraphs of Article 6 of the Regulation on the Technical Assessment of Electricity Generation Applications, published in the Official Gazette dated 20.10.2015 and numbered 29508, YEPDİS has been sent to our General Directorate for the technical evaluations of the electricity generation facilities based on unlicensed electricity generation. Approved coordinate application plan and Technical Evaluation Form Documents for Unlicensed Electricity Generation Applications Based on Wind Energy must be submitted via Land Registry and Cadastre Offices or Licensed Map Cadastre Offices.

    The technical evaluation reports of the applications based on wind energy, whose technical evaluation is deemed appropriate by our General Directorate every month, are available in the link below and the applications in the organized industrial zones are included in the link of the network operator in charge in the region.

    The technical evaluation reports of applications based on wind energy, whose technical evaluation is deemed appropriate by our General Directorate every month, are available in the link below.

    Mainly YEKA; These are areas where electricity generation plants based on wind and / or solar energy resources can be established in large installed powers with economic potential, which do not prevent establishment in terms of administrative permits, are technically suitable to be established and operated.

    In general, we can list the main objectives of YEKA in the following items;

    • Prioritizing economic areas in terms of wind and solar energy potential,
    • To identify areas that are technically appropriate and efficient to be established,
    • To reveal areas that do not have any administrative problems in the establishment of wind and / or solar power plants,
    • Planning the areas to be determined, taking into account the areas that are forbidden to establish administratively and their safety distances, and carrying out environmentally sensitive projects, not against the environment,
    • To minimize the effects of renewable energy sources on the grid by determining the resource areas by taking into account the existing transmission infrastructure and investment projections,
    • To ensure that the transmission infrastructure planning projections are tailored to the resource areas in line with the needs,
    • To ensure that economic projects are carried out primarily in terms of the country's economy,
    • To ensure that the transformer capacity is reserved in areas suitable for the establishment of WPP and SPP,
    • To eliminate wasted time and cost items in renewable energy investments,
    • To assist the energy supply security by providing the allocation of real areas to the real investor, as the areas to be determined are projects ready for the construction period, and by the effective commissioning of investments in the short term.

    In order for an area to be declared as YEKA, analysis and planning of such areas have economic resource potential in terms of electricity generation, there are no restrictions that would prevent it from being established or operated technically, it is an environmentally sensitive investment and that the produced electricity can be transferred to the transmission system reliably. needs to be done. With the YEKA method, investments can be put into operation much more quickly as all the criteria are taken into account at the beginning of the process, and the way to reach the determined targets is opened more easily. Since YEKA has been freed from the necessary permit processes, the investments will start in the direct construction process and only real investors will be enabled to operate. Finally, with the adoption of the resource area determination method that will be applied as an alternative to the current licensing process, it is thought that with the commissioning of the projects in a much shorter period, large installed powers will be reached in a short time and thus, our country can reach its renewable energy targets. Adopting the principle of realizing economic projects primarily with YEKA, the projects will be put into operation in a short time, as well as the evaluation of the best resource areas, thereby generating profitable investments for the public and private sectors.

The method of determining YEKA includes the analysis of countries' resource potential, current transmission infrastructure and the mer legislation applicable to energy investments in that country. This method is based on the screening criteria and can generally be classified in five stages. The following section describes the issues and steps to consider when determining resource areas.

Stage 1 - Identification of Areas with Potential Above the Minimum Threshold:

When determining resource areas, firstly, the minimum threshold potential values should be calculated by taking into consideration the economic recycling periods of energy investments. Threshold potential values may differ from country to country according to the types of technology to be applied, investment and operating costs, sales prices of electricity produced and incentive systems. The purpose of this stage is primarily to identify the economic investment zones. Within the scope of YEKA, the renewable energy resource areas below the threshold potential value should be removed from the scope of the study and the search for the resource area over the remaining areas should be continued.

Stage 2- Determination of Unused Areas in Terms of Administrative Permits:

YEKA method aims to develop environmentally friendly renewable energy projects. The fact that the candidate source area has the potential to produce electricity does not mean that it is sufficient to be the source area of ​​that region alone. The designated resource areas should not be included in areas forbidden to establish renewable energy power generation plants in terms of administrative and legal permits. Administrative forbidden areas, which may differ from country to country and energy resource type, should be excluded from the search for resource area. Thus, the problems that may be experienced in terms of administrative permits will be taken into consideration when planning the project in the first place. Within the scope of the YEKA study, revealing areas that are not used in administrative terms is one of the most important stages of these studies. Because continuing to work in an area where the right of land use cannot be obtained causes material and temporal losses in the process. Within the scope of the Electricity Market Licensing Regulation published in the RG dated 28.11.19 dated 02.11.2013 and the Environmental Impact Assessment Regulation published in RG dated 25.11.2014 and numbered 29186, the areas and the required safety (approach) distances that are required by the administrative institutions for renewable energy investments. It was investigated.

    Since the installed powers of the energy plant areas to be determined within the scope of the source area will be large, these areas must be planned in an environmentally friendly manner. For this purpose, the following are the areas where energy investments are not allowed under the applicable legislation.

    •  "National Parks", "Natural Parks", "Natural Monuments" and "Natural Reserves" as defined in Article 2 of the National Parks Law and determined according to Article 3 of this Law, 
    •  "Wildlife Safeguarding Areas, Wildlife Development Areas and Wildlife Placement Areas" as determined by the Land Hunting Law; 
    • Areas for which the "Cultural Assets", "Natural Assets", "Site" and "Protection Area" are identified and registered as "Cultural Assets", "Natural Assets", "Site" and "Reserve Area" in sub-paragraphs (a) 1, 2, 3 and 5 of Article 3 of the Law on Protection of Cultural and Natural Assets (csb.gov.tr, July 8, 2015), 
    • Areas designated and declared as "Special Environmental Protection Areas" by the Council of Ministers in accordance with Article 9 of the Environmental Law, 
    • Wetlands mentioned in the Regulation on the Protection of Wetlands and 2.5 km injunction zones surrounding these areas 
    • Bird migration routes in Istanbul, Kocaeli, Çanakkale, Tekirdağ, Hatay and Artvin provinces as part of Circular No. 2014/1 issued by the Ministry of Forestry and Water Affairs on March 3, 2014, 
    • Prohibited zones in accordance with the Regulation on Military Prohibited Zones and Security Zones, put into effect by the Council of Ministers Decree No. 83/5949 dated January 17, 1983, 
    • Protected areas according to the Bosphorus Law, i. Protected Areas of the "Important Sea Turtle Reproductive Areas" (Areas of the "Convention for the Protection of Wildlife and Living Environments of Europe"), Areas of Protection I and II, "Areas for Living and Reproductive the Mediterranean Sea", 
    • Protected areas under the "Convention on the Protection of the Mediterranean Against Fouling" (Barcelona Convention)
    • Coastal areas that are the habitat and nutrition environment of the "Mediterranean Endangered Sea Species" included in Article 17 of the Genoa Declaration, 
    • Cultural, historical and natural areas that are granted the status of "Cultural Heritage" and "Natural Heritage" protected by the Ministry of Culture in accordance with Articles 1 and 2 of the World Convention on the Protection of Cultural and Natural Heritage,
    • Areas under protection in accordance with the "Convention on the Conservation of Wetlands of International Importance especially as Waterfowl Habitat" (RAMSAR Convention),
    • Areas that are important for scientific research and/or that are endangered or fall-out species and the habitat of species that are endemic to our country, biosphere reserve, biotopes, biogenetic reserve areas, unique geological and geomorphological formations, 
    • Areas where a construction ban has been imposed as per the Coastal Law, 
    • Aquaculture Products and Reproductive Areas under the Water Products Law, 
    • Areas defined in Articles 17, 18, 19 and 20 of the Water Pollution Control Regulation, 
    • Lakes, rivers, groundwater operation areas, 
    • Windlicense/licensed wind and solar power plant areas, 
    • Wind and solar power plant areas covered by unlicensed electricity generation, 
    • Valuable mining sites licensed from the General Directorate of Mining Affairs, 
    • Pit, fountain, welding, sealing, tunnel, gallery, etc. for the designated protected areas. buildings are protected in the absolute protection areas (50 - 100 m) and first degree areas, 
    • Drinking and drinking water absolute and short-distance protection areas until special provisions for potable water basin are introduced.

    Stage 3 - Determination of Non-Dryable Areas in Terms of Technical Criteria:

    It is desired that the installation of an electricity production plant is as easy as possible and that its operation is smooth. In the resource areas to be determined from this point of view, it is necessary to set out the criteria that may lead to technical problems in the installation and operation of the welding areas, and in economic terms, extra costs. These criteria vary depending on the type of renewable energy source, where the topography of the land, the size of the resource area depending on the installed power and the natural conditions that need to be considered on a regional basis should also be considered.

    Stage 4- Examination in terms of Electricity Transmission Infrastructure:

    Power plants based on renewable energy sources produce variable and diffused electricity due to the nature of the sun and wind. In this respect, the current electricity transmission infrastructure of the system operator should be taken into consideration in order to transfer the electricity generated from the power plant to be installed in the source area to the network reliably. The carrying capacity and electricity supply-demand balances of the existing transmission line are a determining factor in the capacity of the generation facility to be established. If there is no suitable transmission capacity close to the source area, how to make an additional investment according to this area should be evaluated at this stage on a technical and economic scale.

    Stage 5 - Making the Economic Priority Ranking of the Determined Resource Areas:

    In YEKA determination methodology, priority planning of the resource areas to be determined in terms of the country's economy is required. At this last stage, analyzes will be made on the economic assumptions of resource areas determined technically and administratively and evaluations will be made. It is aimed to realize the most economical projects as priority in the short term by making comparisons between the determined resource areas.

    In the method of determining the source area, it will be ensured that more environmentally friendly projects are realized due to the consideration of the prohibited areas and safety distances against the environmentally hazardous effects of the electricity generation plants to be installed. In addition, by revealing the places with high resource potential, it will be possible to benefit from the renewable energy potentials by making the current electricity transmission infrastructure development plans taking into account these areas.

    There are many candidate resource areas that can be developed in our country. Since it is not possible to work separately for each area from the transmission perspective and the questioning of the source areas in terms of administrative and technical aspects, the first thing to do is to start the analysis from the areas with high resource potential.

    1. Working Groups

    The process of identifying resource areas needs a coordinated and detailed working process. YEKA working groups consist of two sub-working committees, technical and administrative. The technical committee includes EIGM on behalf of MENR, which will identify the resource area and examine its production potential technically, and TEİAŞ, which will evaluate the transmission of the generated electricity to the network in terms of transmission infrastructure. In the sub-working groups of the administrative committee, candidate resource areas will be evaluated in terms of land ownership, zoning permits and environmental impacts, and the relevant local governments and the Ministry of Environment and Urbanization should be included in this committee. All these studies will be reviewed by our Ministry and EMRA as the Monitoring Committee and the determination process will be finalized.

    2. Investigation in terms of Regional Technical and Administrative Permits

    Another stage to be considered while conducting the resource area of the regions that may be suitable for the transmission infrastructure is to evaluate the land in terms of geological studies, ownership, environmental impacts and the zoning process. In this process, it is necessary to work with the relevant local governments and the Ministry of Environment and Urbanization. The main studies that need attention are given below.

    a. Land Geological Studies

    b. Land Ownership

    c. Local zoning restrictions

    D. Finding an existing or projected structure

    to. Land Permits

    f. Environmental Effects

    3. Evaluation of Electricity Transmission Infrastructure

    Electricity transmission infrastructure is an indispensable issue in order to transfer the produced electricity to the network safely. The point to be considered in the process of determining the resource area; The relationship between searching for the potential of the source where the transmission lines are present or whether the transmission lines should be brought to the places where the source areas exist is similar to the dilemma “chicken or hatch, egg or hatch”. For this purpose, detailed technical and economic analysis between high quality welding areas and electricity transmission infrastructure should be made. Resource areas can be grouped under two groups in terms of transmission infrastructure. These;

    1. Available Fields: These are areas with high quality welding potential and close to current or planned electricity transmission lines. The distance to the transmission lines; It may vary depending on the size of the source area, its potential and the current carrying capacity of the transmission line in that region.
    2. Developable Areas: These are the areas where the source potential is high but there are no electricity transmission lines or distant to transmission lines and areas with transmission lines but without high source potential. In terms of transmission infrastructure, the size of the welding areas can be determined as a result of analysis of the production and transmission models to be carried out in order to transfer the generated electricity reliably to the voltage levels of the transmission lines close to the source area, the current carrying capacities depending on the type of conductor used. In order to ensure maximum benefit from the welding area, it is necessary to make transmission line investments in accordance with the production potential of the welding areas.

    Projects to be implemented primarily among selected resource areas should be selected according to the country's economy and energy system requirements. Accordingly, reduced electricity production cost (LCOE) prices for each determined resource area should be calculated and projects with the lowest cost should be implemented primarily in order to provide maximum benefit for the country's economy. In addition, it is important to make sources with variable production characteristics such as solar energy close to the points where consumption is more, in order to minimize the effects on the grid. This is another point to be taken into account in the realization of resource areas as a priority.

    In the YEKA determination method, areas ready for investment are created by taking into consideration the permissions and approvals required for the establishment of the electricity generation plant. With the directing of the investments to these areas, the loss of time for the permits that the investors should obtain during the associate degree period will be prevented within the scope of the provisions of the Electricity Market License Regulation. Thus, investments will be provided to enter the business more quickly. How these resource areas will be allocated to investors may vary depending on country requirements. Below are the methods that can be followed for YEKA allocation.

    1. Making allocations to investors with an incentive price for each resource area, taking reference to the reduced electricity production cost per kWh calculated separately for each resource area,

    2. In our country, which aims to reduce the dependency on foreign production in renewable energy technologies by encouraging domestic manufacturing, making allocations to companies producing domestic equipment from these areas by considering their annual production capacities,

    3. Allocating these areas to the investors in exchange for the land use fee, and allocating the electricity produced by allowing bilateral agreements to be sold in the market,

    4. Due to the large scale of the power plants to be installed in the designated resource areas, these investments are made and operated by the state in terms of their importance in terms of energy supply security and the operation and maintenance of these power plants are relatively easy compared to those based on other sources.

    Finally, EMRA will be licensed in accordance with the provisions of the Electricity Market Law No. 6446 in order for the electricity generation plants to be established in the resource areas to operate in the electricity market.

    With the rapidly increasing world population and industrialization, the need for energy is increasing day by day. Approximately 80 of the world's electricity needs are met from fossil sources. However, due to the rapid decrease of the reserves of fossil resources and environmental pollution, different solutions were sought. In addition to being sustainable, renewable energy sources have gained importance due to their availability all over the world and their environmental impact is very low, and have caused countries to change their energy policies. According to the World Energy Outlook report, it is predicted that by 2040, renewable energy investments will be much more competitive and the share of renewable energy within the total electricity generation share in the world will reach 34% from 21%. It is estimated that the largest shareholder in this development will be wind and solar energy. Due to the increasing energy demand and the danger of the depletion of conventional resources, the use of renewable energy resources has gained importance especially in recent years, and it is foreseen that its importance will increase with the coming years. Countries implement various incentive mechanisms to encourage renewable energy investments. With the decrease in technology prices, it has become more important to operate in areas with suitable potential rather than incentive mechanisms for the renewable energy based electricity generation facility investments, which started to compete with conventional sources.

    Sample applications in the USA, England and Germany, which use the method of determining the source area in the world, are examined. In the license process applied in our country, the time between the development of a power plant project and its operation takes 6-7 years on average, or it is observed that the projects are canceled due to the failure to obtain the necessary permits, whereas in the application of the method of determining the resource area in the world, it is observed that the plants are put into operation for an average of 2-3 years. The general working principle of the method of determining the source area is based on the selection criteria. The criteria to be determined may vary from country to country depending on factors such as the energy potential of countries, the legislation of mer, technology types, system costs and energy targets.

    The National Energy and Mining Policy announced by our Ministry is built on "energy supply security", "localization" and "predictable markets". "more domestic and more renewable" approach has been adopted. In the framework of these policies based on local production and R & D base and Türkiye work to do in this area, it is meticulously executed. Employment and R & D and investments in progress, aimed at providing a contribution to the current account deficit and lowering Türkiye's exports. We have a strategy and policy based on energy supply security, alternative energy sources, resource diversity, the introduction of domestic and renewable resources into the economy, sustainability, liberalization in energy markets and energy efficiency. In this context, our main strategies and policies are to ensure the diversity of resources by prioritizing domestic resources, to increase the share of renewable energy resources in energy supply, to bring full functionality to free-market conditions, to improve the investment environment and to increase energy efficiency. Türkiye, wind, solar, hydroelectric, geothermal, biomass, and sustainable marine renewable energy resources and to develop and systematically seeks to use. In addition to providing renewable energy, supply security, and resource diversity, it is also important in terms of transition to a low carbon economy, its contribution to sustainable development with innovative approaches and new technologies. Studies are carried out to create an energy sector that complies with our strategies and policies. Our country, which has a rich renewable energy potential in terms of reducing our high foreign dependency on energy and ensuring sustainability in energy supply, should also use these resources effectively. Due to its economic resource potential, domestic and foreign investors show great interest in establishing an electricity production plant based on renewable energy resources in our country.

    Technical, administrative, and economic criteria have been introduced and basic standards have been developed in order to determine the resource areas in our country. First of all, this criterion is the “Regulation on the Procedures and Principles Regarding the Determination, Rating, Conservation and Use of Renewable Energy Resource Areas for Electric Energy Production” published in the Official Gazette dated 27.11.2013 and numbered 28834. By creating large-scale renewable energy resource areas (YEKA) in public and treasury real estate and private property, efficient and efficient use of our renewable energy sources, the realization of investments with the allocation of these areas to investors, and the parts containing advanced technology used in electrical energy production facilities based on our renewable energy resources. The Regulation on Renewable Energy Resource Areas was published in the Official Gazette dated 09/10/2016 and numbered 29852 in order to ensure that it is produced domestically or supplied domestically and contributes to the technology transfer. With this Regulation, a new model has been launched in the evaluation of renewable energy sources. Thanks to the YEKA model;

    Large-scale renewable energy resource areas (YEKA) will be created in public and treasury real estate and private property, and renewable energy resources will be used more effectively and efficiently,

    • Our renewable energy resources will be established with components or plant components with high domestic contribution and high technology,
    • Contributions will be made to ensure technology transfer and Research and Development activities will be developed in our country on renewable energy issues in our country,
    • Our electricity transmission and distribution system will be operated more safely,
    • The electricity to be produced in YEKA's will be provided to be purchased in more economical conditions according to market prices,

    Serious employment will be provided thanks to the factories to be established within the scope of the Domestic Production Provision Allocation (LOAD) model.

    The studies for determining new YEKAs based on wind and solar energy and organizing competitions are continuing by our Ministry. YEKA competition of the new ones also will provide a significant acceleration in the assessment of Türkiye's renewable energy potential result of the performance, our country will increase its investments in renewable energy, but also the logistic advantage of our the country in economic strength, will have positive effects in becoming an important center with qualified staff competence is assessed.

    In our country, minimum threshold values ​​have been calculated for the areas with economic potential in order to determine the resource areas within the ministry and RES-GES has been established with the relevant public institutions in order to reveal prohibited areas.

      • Fields that can be evaluated as solar energy resource areas (Candidate YEKA) are determined
      • The works for setting up and operating measurement stations on candidate YEKAs, analyzing the data and preparing technical / economic feasibility reports are carried out.
      • Candidate YEKAs are graded and priorities are determined.
      • For candidate YEKAs, which are considered to be declared as YEKA, connection capacity information is obtained from TEİAŞ and administrative opinions are obtained in coordination with other institutions and organizations regarding these areas.
      • Eligible Candidates YEKAs are announced as YEKAs in the Official Gazette.
      • Draft Specification and YEKA Right of Use Contract drafts are prepared for the allocation of the usage rights of YEKAs and connection capacities.
      • Use rights competitions are held for YEKAs.

      YEKA SPP - 1  KARAPINAR PROJECT

      Our first application within the scope of YEKA Regulation was carried out in Konya / Karapınar. In the competition held in our Ministry on 20.03.2017, the lowest sales price was offered with 6.99 USD-cent / kWh and it is guaranteed to be purchased for 15 years from the date of the approval of the YEKA Usage Right Agreement. An area of ​​27.19 km2 in Karapınar has been designated as Renewable Energy Resource Area. An electric power generation facility based on solar energy with a capacity of 1000 MWe was established in 19,19 km2 of this area. With the establishment of the environmentally friendly and solar-based production facility to be established, approximately 1.7 billion kWh of electrical energy will be produced each year and the annual electricity needs of approximately 600,000 houses will be met every year. In the electricity generation facility that will be operated for 30 years; photovoltaic (PV) solar modules to be manufactured in our country in an integrated manner and auxiliary components with domestic goods certificate to be obtained from domestic producers will be used. Starting from ingot production, PV solar module will be produced from the legal person who won the competition for the utilization of Karapınar YEKA area and the allocation of connection capacity of 1000 MWe. Also;

      The establishment of the "Research and Development Center" and carrying out R&D activities for at least 5 different subjects to be determined within the framework of the R&D plans for 10 years, (It is requested within the scope of the contract that the R&D Center is established and put into operation within 21 months.)

      Kurulması Establishment of an integrated PV solar module production factory with modern techniques and technologies and best practice examples and a minimum production capacity of 500 MWP / year,

      Uygulanması FV solar modules produced in the factory and the plant components having the certificate of domestic goods are applied in Karapınar YEKA field (thus, the high domestic contribution rate will directly and indirectly contribute to the economy of our country.)

      The electrical energy production facility to be established in Karapınar must be completed within 36 months from the date when the integrated factory starts production. In addition, together with the auxiliary facilities of the integrated factory, it is required under the contract in order to provide the relevant environmental, occupational health and safety and other operational standards. The total domestic contribution rate of the PV solar modules to be produced in an integrated manner at the factory will be at least 60% for the first 500 MWp generation and at least 70% for the second 500 MWp generation. It is guaranteed to purchase the electrical energy to be produced from the facility for a period of 15 years from the date of the approval of the YEKA Usage Right Agreement with the lowest sales price of 6.99 USD-cent / kWh determined in the competition. In exchange for the utilization of the Karapınar YEKA area and the allocation of the connection capacity of 1000 MWe; There is a minimum of 90% domestic employment in the installation and operation of the electrical power generation facility and in the operation of the factory, blue and white collar separately, and at least 80% in R&D activities.

       

       

      The processes and developments specified in the specification and YEKA Regulation are followed / executed with the YEKA Usage Rights Agreement signed between the Company that won the YEKA Use Rights Contest for Karapınar YEKA-1 SPP and our Ministry. With the pre-license application to be made by the Company for Karapınar YEKA-1 SPP, it helps to carry out the land allocation, permits, licenses and other works needed in the activities of construction and operation period and coordination with other institutions and organizations is provided. Their demands regarding possible company transfers are evaluated / finalized. Production and research / development activities are monitored / monitored by the factory and R&D Center installations to be established within the scope of the YEKA Right to Use Agreement.

      YEKA - WPP 1 PROJECT

      Our second application in YEKA studies was made in YEKA-WPP. The competition announcement regarding the allocation of the total 1000 MWe connection capacities to be held in the connection regions determined in the YEKA - WPP application was published in the Official Gazette dated 13 April 2017. Within the scope of the said Regulation, after the applications were received by our 8 consortiums established between turbine suppliers and investors based on wind energy until 27 July 2017, 3.48 USD-cent / kWh, which was proposed as a result of the contest held according to the open reduction method on 03.08.2017. It was taken from the lowest sales price and YEKA Usage Rights Agreement was signed on 26/02/2018.

      As a result of the completion of the works related to the eligibility of candidate YEKA on the basis of Connection Regions by the winner of the competition, the proposed sites will be announced as YEKA. YEKA-RES competition conditions will be provided by the characteristics of the Wind Turbines to be installed in YEKAs, the supply and / or manufacture of the parts to be used in the manufacturing of the wind turbines at the desired Domestic Contribution Ratios, and by the establishment and operation of the factory where the wind turbine assembly will be installed. . In line with the specification and draft contract with the company that won the competition;

      1. The license period for the electricity generation facilities to be established within the scope of the YEKA-WPP-1 competition is 49 years, and the electricity to be produced will be purchased for a period of 15 years from the date of the approval of the YEKA Usage Right Agreement at the sale price of 3,48 USD-cent / kWh. With the commissioning of the facilities to be established, approximately 3.5 billion kWh of electrical energy will be produced each year, and annual electricity needs of approximately 1,200,000 houses will be met every year. As a result of the competition, an investment of approximately USD 1.2 billion will be made for the factory, R&D center and all of the WPPs. This investment size will trigger many sectors together with direct and indirect employment and contribute to their development.
      2. By the Winner of the Competition; A factory that will produce wind turbines will be established by bringing together the parts of which are produced and / or supplied according to the desired domestic contribution rates, which are certified by local goods, and the total localization rate will be minimum 65%. The factory will start production in 21 months and it is planned to be established with a wind turbine production capacity of at least 150 pieces / year or 400 MW / year in a single shift.
      3. The R&D center will be established within 21 months and R&D activities will be carried out for 10 years in which high value added outputs will be achieved in wind energy technologies. 50 full-time technical personnel to be employed for 10 years within the framework of R&D plans for at least 5 (five) activities in total, with a minimum of 3 (three) R&D activities in line with the R&D focus subjects for each year. R&D with a minimum budget of 2 (two) million USD for the first year, minimum 3 (three) million USD for the second year, and a minimum of 5 (five) million USD each year, excluding fixed values ​​and machinery - equipment investments. activities will be carried out. firstly the nature of open innovation to support the technology transfer offices of universities in Türkiye, incubation centers and so on. entry-level initiative projects can also be supported.
      4. WPPs will be established in the desired connection regions, provided that they are in 5 different connection regions (Kayseri-Niğde, Sivas, Edirne-Kırklareli-Tekirdağ, Ankara-Çankırı-Kırıkkale and Bilecik-Kütahya-Eskişehir). Among these connection areas, it is essential to install RES at a minimum power of 280 MW in the “Edirne-Kırklareli-Tekirdağ” connection region. The minimum power of the wind turbines to be produced at the factory will be 2.3 MW. Especially with the necessity of producing wind turbines with high localization rate, great contributions will be made to the development of the supplier industry (suppliers).
      5. At least 90% (ninety) local employment, blue and white collar, and at least 80% (eighty) in the R&D activities are mandatory in the establishment and operation of the factory.

       

       

      R&D Fields of Activity:

      • Rotor wing design
      • Generator design
      • Increasing the turbine tower carrying capacity
      • Network frequency management and energy storage system
      • Operational excellence center installation and operation
      • Control software
      • Material technologies and production techniques
      • In innovative gearbox heads,

       

       

      YEKA WPP-2 PROJECT

      YEKA-WPP-2 Competition Announcement was published in the Official Gazette dated 07.11.2018 and numbered 30588 within the scope of the Regulation on Renewable Energy Resource Areas published in the Official Gazette dated 09.10.2016 and numbered 29852.

      A maximum of 20 wind power plants (WPPs) will be installed and operated with a total capacity of 1000 MW. Wind turbines and plant site components with domestic goods and having the desired domestic contribution rates will be used in all WPPs to be established. Depending on the power of the wind turbines to be produced at the factory, approximately 300 to 400 wind turbines will be installed.

      For YEKA WPP-2 competition with a total power of 1000 MWe based on wind energy, connection areas with high wind potential and RES capacities (Balıkesir - 250 MWe, Çanakkale - 250 MWe, Aydın - 250 MWe and Muğla - 250 MWe) have been determined and 30.05 for these regions. Competitions were held in 2019.

  • Enerji Diplomasisi