Licensed Electricity Generation

Enerji Verimliliği

Lıcensıng Processes For Generatıon Facılıtıes Based On Renewable Energy Sources

1.    DESCRIPTION OF LINKING AREAS AND CAPACITIES
2.   ACQUIRING THE RIGHT TO USE THE INSTALLATION OF WIND / SOLAR STATION ACCORDING TO THE TYPE OF THE FACILITY BY THE COMPANY ESTABLISHED BY THE COMPANY ESTABLISHED FOR ELECTRICITY GENERATION ACCORDING TO THE TURKISH COMMERCIAL CODE
3.    WIND - SOLAR MEASUREMENT FOR ONE YEAR PERIOD ON THE PROJECT SITE OR THE REPRESENTATIVE SITE
4.    PREPARATION AND APPLICATION OF THE ASSOCIATION APPLICATION FILE

  • Approval of the “Measurement Station Installation Report hazırlanan prepared for the established measurement stations by the General Directorate of Meteorology or Accredited institutions
  • Sending measurement data for at least 1 year to General Directorate of Meteorology or Accredited organizations
  • Approval of “Measurement Result Report ca by General Directorate of Meteorology or Accredited institutions at the end of 1 year
  • Preparation of application information and documents announced by Electricity Market Licensing Regulation and EMRA Board Decisions
  • Application for associate degree on the dates announced by EMRA Board Decisions
  • Pre-examination of the Associate Degree application by EMRA

5.    TECHNICAL EVALUATION OF THE APPLICATION BY EIGG FOR PRE-INVESTIGED APPLICATIONS
6.    COMPLETION OF THE CONNECTION AR COMPETITION ”PROCESS BY TEIAS FOR THE APPLICATIONS MADE IN THE SAME AREA IN THE TECHNICAL EVALUATION
7.    SUBMISSION OF THE APPLICATION TO UNDERTAKE THE EMPLOYER TO UNDERSTAND THE MAXIMUM FEE FOR THE UNIT “MW” INSTALLED POWER
8.    GIVING “PRELIMINARY” BY EMRA TO THE WINNER OF THE COMPETITION
9.    RECEIVING ALL KINDS OF ADMINISTRATIVE PERMITS FOR FACILITY INSTALLATION BY THE COMPANY DURING THE PRELIMINARY PROCESS - ZONING PLAN APPROVALS - PROJECT APPROVALS
10.    GIVING PRODUCTION LICENSE BY EMRA
11.    COMPLETION OF CONSTRUCTION - FACILITY ACCEPTANCE

  • Approval of the projects of the facility by MENR or the institutions authorized by MENR
  • Completion of construction and installation Works
  • Acceptance of the facility by MENR or institutions authorized by MENR

12.    BUSINESS

Note: Measurements are made for associate degree applications based on wind and solar energy only.